On Friday night, the northbound section of the Abernethy Bridge was still resting on its original supports. By 12:30 a.m. Monday, November 23, traffic was crossing the Willamette River again on the same structure, now about eight feet farther out. The move between Oregon City and West Linn was the first of two slides that will make room for a new section of roadway down the middle of the bridge.
How do you move a bridge?
The first move was just two inches. Crews used hydraulic jacks to lift the bridge deck clear of its supports. A second set of jacks then pushed it sideways at a controlled pace of about four inches every 15 minutes until it was in position on newly widened, earthquake-resistant piers.

Before the first truck could cross, crews had to inspect the structure, reconnect the joints between the bridge and its approaches, restore the lighting, and repaint the lane markings. For drivers back on northbound I‑205 Monday morning, the most noticeable change was the shift in the travel lanes.
The southbound side is next
Crews will repeat the operation on the southbound side on a separate weekend, with the date still to be announced. They’ll move that section in the opposite direction, leaving about 16 feet of space between the two sides for a new section of bridge deck. The Oregon Department of Transportation chose this method because it costs less and causes fewer disruptions than building a new bridge.
In the meantime, overnight lane closures are scheduled in both directions of I‑205 on Monday, November 23, and Tuesday, November 24, from 10 p.m. to 5 a.m. The southbound Exit 8 ramp to OR‑43 is also scheduled to close both nights from 7 p.m. to 5 a.m. All times are local.